# Delivery Forecasting with Monte Carlo Simulation: Committing to Dates with Probabilities

Author: Marin Niehues, Niehues Consulting · Published: 2024-05-02 · Delivery & Steering
Source: https://www.niehuesconsulting.de/en/blog/delivery-forecasting-monte-carlo-simulation/

A Monte Carlo simulation forecasts delivery dates by recombining a team's recent weekly throughput at random thousands of times and deriving a distribution of possible completion dates. Instead of one date you get a statement such as "85 per cent likely by the end of July". The method needs no estimates in hours or points, only the number of items a team actually finishes each week.

This article explains the method through a worked example, shows which data you need, and describes how to present the results to the executive board and to customers without promising a date that nobody can keep.

**A deadline is a bet on the future. A Monte Carlo simulation puts the stake on the table: every date comes with a probability, and the executive board chooses the risk it is prepared to take.**

## What is a Monte Carlo simulation in delivery forecasting?

A Monte Carlo simulation plays through the future of an undertaking many thousands of times, each time with values drawn at random from the past. The name goes back to the method that Nicholas Metropolis and Stanislaw Ulam described in a 1949 paper on the Monte Carlo method. In software development and project work it was popularised by, among others, Troy Magennis and Daniel Vacanti, whose book "Actionable Agile Metrics for Predictability" appeared in 2015.

The simulation works like this. You know your team's throughput, meaning the number of items completed per week, for the past twelve weeks. For each simulated run, the computer picks one of those twelve values at random for every coming week, adds the weeks up until the backlog is cleared, and records the number of weeks needed. It repeats this ten thousand times. The ten thousand results form a distribution: so many runs finished after nine weeks, so many after ten.

You read the result as percentiles. The 50th percentile gives the number of weeks that sufficed in half of the runs, and the 85th the number that sufficed in 85 of 100 runs. For commitments to third parties, teams usually use the 85th or 95th percentile.

## Why are averages dangerous for deadlines?

Averages are dangerous because a date based on the average is missed in about half of all cases. Sam Savage, a consulting professor at Stanford University, described this in his 2009 book "The Flaw of Averages": plans based on average values go wrong on average.

An example shows the scale. A team completes 4.75 items a week on average, and the backlog contains 40 items. Dividing gives 8.4 weeks, and the team promises eight. The spread of the weekly values is about 1.45 items. After eight weeks the team has on average completed 38 items, and the probability of reaching 40 or more is just under one in three. Two out of three deadlines of this kind are therefore missed, even though each individual calculation looked correct.

Estimates in hours or story points also tend to fall short of what actually happens, because they leave out waiting time, interruptions and rework. Throughput measures what was actually finished after all those influences.

## How do you calculate a delivery forecast?

You calculate a delivery forecast in five steps, from recording completions to a commitment with a probability attached.

1. Record throughput: count, for each of the last ten to twenty weeks, how many items the team completed. An item counts when it meets the definition of done.
2. Count the backlog: establish how many items are missing for the goal. Slice them to a similar size so that counting is meaningful.
3. Allow for growth: if a backlog tends to grow because items split during work, include a growth rate. If the list typically grows by a fifth, calculate with 48 items instead of 40.
4. Run the simulation: a spreadsheet is enough for the calculation, as is a small script or one of the freely available community tools.
5. Read off the percentiles: state the 50th, 85th and 95th percentile together with their probabilities.

**Example: forecast for a team completing 4.75 items per week**
Criterion | Backlog of 40 items | Backlog of 48 items (with growth) | Consequence for the commitment
50 per cent probability | 9 weeks | 11 weeks | Internal planning, not a promise
85 per cent probability | 10 weeks | 12 weeks | Commitment to the business unit and the board
95 per cent probability | 11 weeks | 12 weeks | Commitment under contract or with high costs of delay

The values are an approximation using the mean and spread of the twelve weeks in the example. A real simulation over the raw data gives results of a similar magnitude, plus the shape of the distribution, which differs when there are rare outliers. Growth from 40 to 48 items moves the commitment by two weeks, an indication of how much weight the quality of the count carries.

## When is a Monte Carlo forecast reliable?

A Monte Carlo forecast is reliable when four conditions are met: past throughput also holds for the future, items are of similar size, the team remains largely stable, and the number of items in progress at the same time does not fluctuate widely. John Little described the link between lead time, throughput and work started in 1961 in the law that bears his name: the average number of items in the system equals throughput times average lead time. Whoever limits work in progress makes the forecast more stable. The article on [limiting work in progress](/en/blog/limit-work-in-progress-deliver-faster/) shows how.

The forecast loses its value when circumstances change fundamentally: a team grows or shrinks, the type of work changes, or an external dependency delays completion. In these cases you reset the data and calculate with the weeks since the change.

**Which data you need**
- Completions per week: at least ten weeks of history, preferably twenty.
- A uniform counting rule: what counts as an item and when it counts as complete.
- Growth rate: how much the number of items typically grows between planning and completion.
- Change events: dates of team changes, holiday periods or process changes.

## Monte Carlo or estimation: which fits which situation?

The simulation fits teams that deliver steadily and have a history, while estimation fits new undertakings without a data basis. The two methods do not exclude each other: for a new undertaking you begin with a rough estimate of the number of items and replace it with measured values once the team has delivered for a few weeks.

**Comparison of the methods**
Criterion | Estimation in hours or points | Monte Carlo simulation | With Niehues Consulting
Data basis | Judgement of those involved | Measured throughput of recent weeks | Method chosen by data situation and decision need
Effort per forecast | Estimation rounds with the whole team | Counting and calculating, a few minutes | Data capture built into the working routine
Statement | One date | A date with a probability | Commitment graded by risk
Response to change | Re-estimate | Re-simulate once new weeks are available | Forecasting becomes a fixed part of steering

## How do you present forecasts to the board and to customers?

You present a forecast by making the probability the basis of the decision: the board chooses the risk, and the team names the date that goes with it. A commitment at the 85th percentile means that in 15 of 100 comparable cases more time would be needed. Whoever states this number openly moves the discussion from the date to the risk, and to the question of whether scope or budget can be adjusted if an earlier date is demanded.

This also helps with contracts and fixed dates. For an undertaking with high costs of delay you choose the 95th percentile and keep scope ready as a variable element, as the article on [agile fixed-price projects](/en/blog/agile-fixed-price-projects-flexible-scope/) describes. The forecast complements planning across many teams: for dates that depend on several teams, also read the article on [release planning](/en/blog/release-planning-reliable-commitments/).

## Which mistakes occur most often in forecasting?

Four mistakes occur most often. First, teams use too little history, for example only three weeks, and the distribution does not reflect the pattern. Second, they count items of different sizes as equal without splitting the largest. Third, work that is later discarded flows into the figures, so throughput looks higher than the benefit. Fourth, the forecast is made once and never updated, although new weeks would improve the statement. An update after each week takes little effort, and the gap between forecast and reality shows early whether an undertaking is falling out of rhythm. As an early warning system, [flow metrics](/en/blog/flow-metrics-throughput-wip-wait-time/) supply the measures.

## Steering forecasts with Niehues Consulting

[Niehues Consulting](/en/) is a consultancy for AI management and organisation design from a delivery perspective, based in Düsseldorf. Founder Marin Niehues builds organisations that deliver, in projects ranging from VC-funded scale-ups to DAX 40 corporations and in more than 20 countries on six continents. In the service area of delivery management and organisation design he steers delivery as delivery manager, project manager or product owner.

The approach follows the Niehues Delivery Model. Two of its test questions matter most for delivery forecasts: What is the baseline, and how do we measure success? Who is responsible for operations from day one? It follows that data capture and forecasting belong in the team's ongoing steering, where they are refreshed every week. You start with a free initial consultation of 30 minutes, which you can book via the [contact form](/en/#kontakt). The scope and terms of an engagement are discussed in the free initial consultation.

**Conclusion**
A Monte Carlo simulation replaces the single date with a distribution and so makes uncertainty discussable. All you need is the throughput of recent weeks, a clear counting rule and the willingness to give dates with probabilities. Choose the 85th percentile for commitments within the company and the 95th where a contract is involved.

**Sources**
- Metropolis, Ulam: The Monte Carlo Method, Journal of the American Statistical Association, 1949
- Little, John: A Proof for the Queuing Formula L = λW, Operations Research, 1961
- Savage, Sam: The Flaw of Averages, book, 2009
- Vacanti, Daniel: Actionable Agile Metrics for Predictability, book, 2015

## Frequently asked questions

### What is a Monte Carlo simulation in project management?

A Monte Carlo simulation uses values drawn at random from the past to compute many possible courses of an undertaking, and from them a probability distribution for the completion date. It therefore gives a statement such as "85 per cent likely by week 10" rather than a single date. The input is usually weekly throughput.

### What data do I need for a Monte Carlo forecast?

You need the number of items completed each week over at least ten weeks, and the number of items still open. You also need a counting rule that defines what an item is. Estimates in hours are not required.

### How many weeks of history make sense?

Ten to twenty weeks make sense, because they capture fluctuation and still match the team's current situation. Fewer than six weeks give hardly any reliable results. After a change in the team, you reset the history.

### What does 85 per cent probability mean for a deadline?

It means the undertaking was finished by that date in 85 of 100 simulated runs. In the other 15 it took longer. This value is common for internal commitments, and where a delay is costly you choose the 95th percentile.

### Do I need special software for Monte Carlo forecasting?

No, a spreadsheet is sufficient for the method. For ten thousand runs you use a random function and a helper column per run, or a small script. The quality of the numbers matters more than the tool.

### Does Monte Carlo forecasting work with Scrum?

Yes, it works with Scrum just as with Kanban, because it only needs completed items per unit of time. You can use sprints instead of weeks as the unit. The counting rule must apply across the team so that items are comparable.

### What is the difference between velocity and throughput?

Velocity adds up the estimated story points of completed items, whereas throughput counts the completed items themselves. Velocity depends on estimates and how they develop, throughput on observation. Throughput suits Monte Carlo simulation because it needs no estimates.

### When is the forecast not meaningful?

It is not meaningful when there is no history, when the team has changed substantially, or when items vary widely in size. For a new undertaking without data, start with a rough estimate and switch to simulation once a few weeks of measurements exist.
