# Delivery Manager: The Role Between Project Manager and Scrum Master

Author: Marin Niehues, Niehues Consulting · Published: 2024-06-06 · Delivery & Steering
Source: https://www.niehuesconsulting.de/en/blog/delivery-manager-role/

A delivery manager is responsible for making sure the work of several teams reaches the customer reliably, by steering dependencies, commitments as well as risks across team boundaries. The Scrum Master improves the work of one team, and the project manager steers a single project. The delivery manager turns several teams and projects into a programme that keeps its dates and gives management dependable information.

This article separates the three roles, describes the tasks of a delivery manager and sets out criteria for when an organisation needs one.

**The Scrum Guide knows three accountabilities within a team and no role for steering several teams. Wherever several teams work on one outcome, this task arises by itself, and without a named person it is left undone.**

## What does a delivery manager do?

A delivery manager makes sure that agreed outcomes are delivered at the agreed time and quality, even when several teams are involved. The role works on the system in which the teams operate and takes no individual tasks within a team. The tasks fall into five areas.

The first area is delivery planning. The delivery manager brings the teams' plans together into one picture, tests assumptions and makes capacity visible. The article on [capacity planning in agile teams](/en/blog/capacity-planning-agile-teams/) shows how commitments can rest on data.

The second area is dependencies. When team A waits for an interface from team B, responsibility for resolving it belongs to neither team alone. The delivery manager keeps the list of dependencies, brings the parties to one table and follows the resolution through. Methods for this are described in the article on [dependencies between teams](/en/blog/managing-dependencies-between-teams/).

The third area is risks and impediments. Whatever a team cannot solve itself reaches the delivery manager, who takes it to the right level and follows up on the decision. The fourth area is reporting: the delivery manager gives management and sponsors information on progress, deadline as well as risk that is based on data rather than mood. The fifth area is the improvement of the delivery system itself, such as lead times, waiting times as well as the number of parallel initiatives.

## How does a delivery manager differ from a Scrum Master?

A delivery manager differs from a Scrum Master in scope: the Scrum Master works for one team and its way of working, the delivery manager for the outcome across several teams. The 2020 Scrum Guide describes the Scrum Master as accountable for Scrum being understood and effectively applied in the team, and as a servant to the team and the organisation. Committing dates to management is not among the Scrum Master's accountabilities.

The difference shows in three questions. Who improves collaboration within the team? The Scrum Master. Who makes sure five teams deliver a coherent result at the end of the quarter? The delivery manager. And who tells the board whether the October date will hold? Also the delivery manager, based on the teams' forecasts.

## How does a delivery manager differ from a project manager?

A delivery manager differs from a project manager in time horizon and steering logic: the project manager steers a time-limited undertaking with plan, budget as well as acceptance, the delivery manager a continuous delivery system. The seventh edition of the Project Management Institute's standard from 2021 is organised around principles rather than processes and describes projects as part of a system for delivering value. That brings the two roles closer together, yet practice still distinguishes them.

In many companies a project manager takes over the delivery manager role after agile teams are introduced, without the requirement changing. The move succeeds when the project manager stops assigning tasks and starts steering dependencies and decisions. The UK government's Service Manual lists the delivery manager among the roles of a service team and describes the job as setting up the agile working environment, removing obstacles and helping the team organise its own work. The emphasis there, too, is on the team's working system and its obstacles.

**Delivery manager, Scrum Master and project manager compared**
Criterion | Scrum Master | Project manager | Delivery manager
Scope | One team | One project | Several teams or projects
Time horizon | Permanent in the team | Until the project ends | Permanent in the programme
Accountability | Effective use of Scrum | Plan, budget, acceptance | Reliable delivery across team boundaries
Commitments to management | No | Yes, for the project | Yes, based on team forecasts
Steering means | Facilitation, coaching | Plan, milestones | Dependencies, deadlines, metrics
Typical metric | Team improvement | Schedule and budget adherence | Lead time, on-time delivery per quarter

## How does a delivery manager differ from a product owner?

The product owner decides what is built and in which order, and the delivery manager makes sure it arrives. The Scrum Guide makes the Product Owner accountable for the value of the product and the ordering of the Product Backlog. The delivery manager does not interfere with these decisions but shows what the order means for dates and dependencies. How the role works in mid-sized companies is described in the article on the [product owner in the Mittelstand](/en/blog/product-owner-mid-sized-companies/).

On sequencing in particular, the delivery manager helps with a calculation. He or she shows what a postponement costs, and the product owner decides with that knowledge. The basis is prioritisation by the cost of delay, described in the article on [cost of delay](/en/blog/cost-of-delay/).

## When does a company need a delivery manager?

A company needs a delivery manager as soon as three or more teams work on the same outcome or when dates to customers or the board are binding. With two teams, coordination between the two product owners is usually enough. From three teams upwards the number of possible dependencies grows faster than the number of teams: three teams have three possible pairings, six teams fifteen. Every dependency without an owner becomes a source of delay.

**Checklist: Does our initiative need a delivery manager?**
- Do three or more teams work on a shared outcome?
- Are there commitments to customers or the board that affect more than one team?
- Does at least one team regularly wait for results from another?
- Is there nobody who reports progress, deadline as well as risk across all teams with evidence?
- Do impediments that teams cannot solve end up on a list without an owner?
- Can more than a third of missed deadlines be traced to dependencies?
With three or more yes answers the role pays off, and with five or more it is overdue.

The role can be filled in several ways. An experienced project manager can take it on after further training, a Scrum Master can grow into it with experience across several teams, and for the build-up an external appointment is suitable that brings patterns and tools and hands over later. Which variant fits depends on the maturity of the organisation.
## Which skills does a delivery manager need?

A delivery manager needs five skills: an understanding of flow metrics, conflict facilitation, planning methodology, basic knowledge of the product and the ability to speak plainly to executives. Metrics are the tools of the trade, because lead time, throughput as well as work in progress provide the information on dates. Facilitation is the daily business, because dependencies are mostly conflicts over capacity. Product understanding keeps the role from becoming pure administration.

A frequent mistake is to appoint someone who writes reports without bringing about decisions. A delivery manager without access to decision-makers remains a reporter. The role therefore needs a clear mandate from programme leadership: the right to demand decisions, set deadlines as well as escalate dependencies.

## Delivery management with Niehues Consulting

[Niehues Consulting](/en/) is a consultancy for AI management and organisation design from a delivery perspective, based in Düsseldorf. Founder Marin Niehues builds organisations that deliver and works on projects ranging from VC-funded scale-ups to DAX 40 corporations, deployed in over 20 countries on six continents. In the service area of delivery management he takes on the role of delivery manager, project manager or product owner and designs the organisation around delivery.

The approach follows the Niehues Delivery Model. Two of its review questions matter for filling the role: who decides, who delivers, who uses? And: who is responsible for operations from day one? Scope and terms of an engagement are discussed in the free initial consultation, which you can arrange via the [contact page](/en/#kontakt).

**Conclusion**
The delivery manager closes the gap the Scrum Guide leaves open: responsibility for the outcome across team boundaries. The role differs from the Scrum Master in scope, from the project manager in duration and from the product owner in the question it asks. From three teams on the same outcome, the role pays off.

**Sources**
- Schwaber, Sutherland: The Scrum Guide, guide, 2020
- Project Management Institute: A Guide to the Project Management Body of Knowledge (PMBOK Guide), seventh edition, 2021
- Government Digital Service: GOV.UK Service Manual, "What each role does in a service team", government guidance

## Frequently asked questions

### What is a delivery manager?

A delivery manager is the person accountable for making sure the work of several teams arrives on time and at the agreed quality. The role steers dependencies, risks as well as commitments and reports to management on the basis of data. The role is widespread in agile practice, for example in UK government digital services.

### What is the difference between a delivery manager and a project manager?

A project manager steers a time-limited project with plan, budget as well as acceptance, whereas a delivery manager steers a lasting delivery system made up of several teams. The roles overlap on dates and risks. In agile organisations a project manager often grows into a delivery manager.

### Does a delivery manager replace the Scrum Master?

No, the roles complement each other. The Scrum Master improves how a team works, and the delivery manager improves delivery across team boundaries. In small organisations with one or two teams, one person can cover both tasks.

### How many teams can a delivery manager look after?

The number of teams depends on the number of dependencies between them. Three teams have three possible pairings, six teams fifteen, ten teams forty-five. The more tightly the teams are interlinked, the less one person can oversee, and with many teams two people or a coordination level share the task.

### What is the difference between a delivery manager and an agile coach?

An agile coach develops ways of working and capabilities in teams and leadership, while a delivery manager answers for the delivery result. A coach advises and leaves decisions with the organisation. A delivery manager holds a mandate to demand decisions and to report dates.

### Can a Scrum Master become a delivery manager?

Yes, provided the person brings experience with several teams, an understanding of planning and numbers, and a mandate from programme leadership. The move requires looking at the system as well as the team and giving commitments to management. A Scrum Master who prefers coaching inside a team stays more effective there.

### Which metrics does a delivery manager use?

A delivery manager uses lead time, throughput, work in progress and on-time delivery per quarter. The number of open dependencies and their age are added. These metrics show early where delivery stalls and support forecasts to management.