# Flow Metrics: Understanding Throughput, Work in Progress and Wait Time

Author: Marin Niehues, Niehues Consulting · Published: 2023-11-06 · Delivery & Steering
Source: https://www.niehuesconsulting.de/en/blog/flow-metrics-throughput-wip-wait-time/

Flow metrics are four measures that show how quickly work moves through a system: throughput, work in progress, cycle time and the age of work already started. They answer questions that utilisation rates and velocity leave open, namely how long an order takes from start to delivery and where it sits in the meantime. Organisations that collect them over a few weeks usually find that most of the cycle time consists of waiting rather than working.

This article explains the measures as defined in the Kanban Guide, shows in a worked example how throughput, work in progress and cycle time relate to one another, and describes how to turn the data into decisions for your delivery organisation. It is written for managing directors and heads of department who want to know why initiatives take longer than planned and who prefer an answer drawn from data to one drawn from impressions.

**The cycle time of a system rises with the amount of work started at the same time and falls with throughput. Anyone who wants to shorten delivery dates will usually find the quickest lever in work in progress and wait time.**

## Which measures make up flow metrics?

Flow metrics consist of work in progress, throughput, cycle time and work item age. The Kanban Guide by John Coleman and Daniel Vacanti, published in 2020, defines them precisely and serves as the primary source for the vocabulary. Work in progress is the number of work items a team has started and not yet finished. Throughput counts the items completed in a period, for example per week. Cycle time measures the span between the start and the finish of a single item, and work item age states how long an item that is still open has already been under way.

Four properties make these measures useful for management. They refer to work items, they can be derived from the timestamps in the ticketing system that already exists, they apply to software teams as much as to procurement or contract review, and they show the effect of decisions within a few weeks. In his 2018 book "Project to Product", Mik Kersten adds flow efficiency to the picture: the share of active working time in the total cycle time. It shows how much of its time an item is actually being worked on and how much it spends in queues.

**The four flow metrics at a glance**
Measure | Definition | Question it answers | Common mistake
Work in progress | Items started and not yet finished | How much work is under way at the same time? | Counting only running projects while orders in queues are missing
Throughput | Items completed per unit of time | How much does the system actually deliver? | Calculating with story points instead of item counts
Cycle time | Time between the start and finish of an item | How long does a customer wait for the result? | Looking only at the average and ignoring the spread
Work item age | Time since the start of an item that is still open | Which work is about to become late? | Noticing old items only when they are finished

## How are throughput, work in progress and cycle time related?

The relationship follows Little's Law, a result from queueing theory published by John Little in 1961: the average number of items in a system equals average throughput multiplied by average cycle time. Rearranged, cycle time is work in progress divided by throughput. A team with 24 tasks started and a throughput of six tasks per week has an average cycle time of four weeks. With twelve tasks started and the same throughput, the figure falls to two weeks.

The law holds for systems that run stably over the period observed: on average as much work enters as leaves, and items do not disappear from the system unfinished. The calculation shows the direction in which cycle times move, and it explains why teams with many parallel tasks deliver later. Whether throughput stays the same after work in progress is reduced can only be seen in measurement over several weeks. In practice throughput often holds up, because fewer context switches and fewer handovers free time. How limiting work affects delivery is covered in the article on [introducing Kanban](/en/blog/introducing-kanban-flow-over-utilisation/).

**Calculation: how much of the cycle time is waiting?**
An example with assumed values: an approval request takes ten working days from receipt to decision. On two days someone works on it actively, on eight days it sits in an inbox, waits for a query or waits for an appointment. Flow efficiency is two divided by ten, or 20 per cent. Eight tenths of the cycle time is wait time. Speeding up the active work by a quarter saves half a day, while halving the wait time saves four days.

## Where does work lose time in an organisation?

Work loses most of its time at the transitions between roles and departments and at decision points. Work is performed in hours and waited for in days or weeks. Five causes recur. The first is the queue in front of a bottleneck, such as a specialist department that reviews for every business unit. The second is handovers where information is missing and a query sends the order back to the start. The third is the bundling of work into large packages that are released only when the last part is finished. The fourth is dependence on other teams whose priorities differ from one's own. The fifth is simply too much work started at once, so that each item receives only a fraction of attention.

High utilisation aggravates these effects. Queueing theory shows that waiting time in a system with fluctuating arrivals grows disproportionately as utilisation approaches full capacity. A department running at 100 per cent utilisation therefore has no reserve for urgent orders and absences, and every disruption lengthens the queue in front of it. The article on [time to market](/en/blog/reduce-time-to-market/) shows where the time between idea and delivery is typically lost.

## How do you introduce flow metrics in four steps?

You introduce flow metrics by first defining the start and the end of the work, then analysing the data you already have, examining the distribution and finally deciding on a measure with a review date. The whole path can be completed in four to six weeks without new software.

1. Define start and end: the team agrees on the event from which an item counts as started and when it counts as finished. From the customer's point of view the end is delivery to the user, not the end of development. How precisely this end must be defined is shown in the article on the [definition of done](/en/blog/definition-of-done-what-done-means/).
2. Collect data: for every completed item, the start date and the end date are taken from the ticketing system or a simple spreadsheet. As a rule of thumb, 30 to 50 items are enough for a first analysis, and clean timestamps matter more than a large quantity.
3. Examine the distribution: instead of the average, a scatter plot of cycle times shows how long the faster 50, 85 or 95 per cent of the items took. The work item age of the open items shows which orders have already passed the 85 per cent mark.
4. Decide and review: the team chooses a measure, for example an upper limit on work in progress or a fixed response time for approvals, and checks after four weeks whether the distribution has shifted.

**From observation to action**
Observation | Likely cause | Action
Long cycle time with high work in progress | Too much started at the same time | Set a limit on work in progress, finish before starting
Wide spread of cycle times | Items of very different size, or blockages without escalation | Slice items to a similar size, make blockages visible daily
Long wait time, short active time | Queue in front of a bottleneck or approval body | Clarify capacity at the bottleneck, give approvals fixed time windows
Many items with a high work item age | Work is sitting there unnoticed | Review the oldest items daily, name an owner
Throughput fluctuates strongly from week to week | Irregular arrivals or peaks of leave and disruption | Smooth arrivals, reserve capacity for disruption

## What mistakes occur with flow metrics?

The most frequent mistakes concern the analysis and the use of the figures. The first is the average: a mean cycle time of ten days can hide that individual items take 40 days, and these outliers generate the escalations in management. The second is confusing throughput with velocity. Velocity adds up estimation points that a team assigns itself and that cannot be compared between teams, whereas throughput counts items. The third is comparing teams on their figures, which creates incentives to cut items into pieces or to smooth data. The fourth is measuring only the development part and overlooking the waiting before the start and after completion. The customer, however, experiences the entire span between the request and the delivery.

The figures become more meaningful when leadership uses them as an instrument for improving the system. Management then asks which rule or bottleneck creates the wait. How teams use such measures after a first year with Scrum is shown in the article on [Scrum in mid-sized companies](/en/blog/scrum-mid-sized-companies-after-first-year/).

## Flow metrics with Niehues Consulting

[Niehues Consulting](/en/) is a Düsseldorf consultancy for AI management and organisation design from the delivery perspective. Founder Marin Niehues builds organisations that deliver, in projects ranging from VC-funded scale-ups to DAX 40 groups and in more than 20 countries on six continents. Within delivery management he works as delivery manager, project manager or product owner and aligns organisations so that work reaches users without unnecessary waiting.

The approach follows the Niehues Delivery Model with its three phases. Three of its review questions matter most for flow metrics: What is the baseline, and how do we measure success? Which roles, decision paths and interfaces does operation need? Which metric shows after 90 days that the solution is landing? A cycle time with its distribution provides exactly this baseline, and a wait at an interface shows which decision paths need to be reorganised. The entry point is a free initial consultation of 30 minutes, which you can arrange via [contact](/en/#kontakt).

**Conclusion**
Flow metrics make visible where work sits before it is delivered. Little's Law links throughput, work in progress and cycle time, and in many processes wait time makes up the larger part of the cycle time. Four weeks of data from the existing ticketing system give you a distribution on which dates and measures can be based.

**Sources**
- Coleman, Vacanti: The Kanban Guide, 2020
- Little, John D. C.: A Proof for the Queuing Formula L = λW, Operations Research, 1961
- Kersten, Mik: Project to Product, IT Revolution Press, 2018
- Vacanti, Daniel: Actionable Agile Metrics for Predictability, book, 2015

## Frequently asked questions

### What are flow metrics?

Flow metrics are measures that describe the flow of work through a system. They include work in progress, throughput, cycle time and work item age. They form the basis for forecasts and for the search for bottlenecks.

### What is the difference between cycle time and lead time?

Cycle time spans the period between the start and the finish of an item, whereas lead time, in the usage common in Kanban, starts when the customer places the request. The two terms are defined slightly differently in different sources, so a team should fix them in writing. Wait time is the difference between the elapsed time and the active working time.

### What does Little's Law say?

Little's Law says that the average number of items in a stable system equals throughput multiplied by average cycle time. With 24 items in the system and six items finished per week, the cycle time is four weeks. The law explains why more simultaneous work slows delivery.

### How do you calculate a team's throughput?

You count the items completed in a fixed period, such as a week. Over many weeks this gives a distribution with a minimum, a mean and a maximum. Count items, not story points.

### How much work in progress is sensible?

A useful starting point is a limit equal to the number of team members or slightly below it. The team then lowers the value step by step for as long as cycle time falls and throughput remains stable. The limit applies to work started, not to items still waiting in the queue.

### What is better, velocity or throughput?

Throughput is better suited to forecasts and to comparisons over time, because it counts items and does not depend on estimates. Velocity remains usable as a planning aid within a single Scrum team. For management, throughput is the more reliable figure.

### What data do you need to collect flow metrics?

For each item you need a start date and a finish date, nothing more. The existing ticketing system usually supplies both. What matters is that start and end are defined consistently across the team.

### Do flow metrics apply only to software teams?

Flow metrics apply to any work made up of countable items, including quotations, purchase orders and approvals. The Kanban Guide describes them independently of industry. They suit the management of processes in business units as much as development.