# Hybrid Project Methods: Combining Waterfall and Agile Sensibly

Author: Marin Niehues, Niehues Consulting · Published: 2024-07-15 · Delivery & Steering
Source: https://www.niehuesconsulting.de/en/blog/hybrid-project-methods-waterfall-agile/

You combine waterfall and agile sensibly by steering the frame and milestones together with approvals on a plan and delivering the work inside that frame in short iterations. The combination pays off wherever one part of an undertaking is bound by fixed constraints such as contracts, hardware or certification, while another part can only be clarified by trying things out. What matters is that each method applies exactly where its strength lies and that the transitions between the two are defined in advance.

This article describes four patterns for hybrid projects, a decision tool with four criteria and the interfaces at which hybrid undertakings fail in practice. It is written for managing directors and heads of department who need a common way of steering in an organisation with both traditional and agile teams.

**A hybrid project works when the boundary between plan-based and iterative steering follows the cost of change. What is expensive to change is planned and approved early, what is cheap to change is clarified in iterations.**

## Why is a single method often not enough?

A single method is not enough because undertakings consist of parts with different costs of change. A production line that is ordered and installed can hardly be altered after delivery. The software that controls it can be adjusted weekly. Anyone who steers both in the same way either plans the software too early and too rigidly or lets the hardware run like an experiment.

The history of waterfall shows that the separation of methods is itself a simplification. In 1970 Winston Royce described in a paper on managing the development of large software systems the sequential approach of requirements and design, implementation and testing, and considered it risky when it runs without feedback between the phases. Later practice turned the warning into a template. The counterpart, the Scrum Guide 2020, describes iterations of one month at most and presumes a Product Goal at which the work aims. Neither text rules out a combination, and practice often demands one: with the seventh edition of the PMBOK Guide in 2021, the Project Management Institute moved from a process-based to a principle-based description and made tailoring the method to the context a principle.

## Which patterns exist for hybrid projects?

Four patterns have proved themselves in practice. In the first, the plan-based frame with agile delivery, the organisation steers budget and milestones as well as approvals on a traditional plan and delivers in sprints within each phase. In the second, the agile core with fixed milestones, teams work iteratively while leadership sets deadlines for board decisions, trade fairs or contract partners as fixed anchors. In the third, the parallel track, one part of the undertaking develops to plan, such as hardware, a building or an installation, and another iteratively, such as software or process design. In the fourth, agile clarification with plan-based rollout, a discovery phase tests iteratively what is to be built, after which it is rolled out in a fixed plan.

Which pattern fits is decided by the nature of the constraints. Fixed-price contracts with acceptance favour the plan-based frame, as the article on [agile fixed-price projects](/en/blog/agile-fixed-price-projects-flexible-scope/) shows. Deadlines tied to external events favour fixed milestones, whose planning the article on [milestone planning in agile programmes](/en/blog/milestone-planning-agile-programmes/) describes. A part with a long procurement time favours the parallel track.

**Choosing between plan-based and iterative**
Criterion | Steer by plan | Steer iteratively | With Niehues Consulting
Cost of change | High, for example hardware, construction or contract | Low, for example software or process | Assessment per sub-project in the business case
Clarity of requirements | Stable and described in an acceptable form | Unclear and clarified only through use | Requirements from business analysis with a baseline
External constraints | Contract, certification or fixed supply chain | No binding date or scope | Constraints recorded as boundary conditions in the plan
User feedback | Possible only at acceptance | Possible in every cycle | Feedback planned into the real process
Result | Frame with approvals | Iterations with review | Joint steering with clear handovers

A simple rule gives orientation. If at least three of the first four criteria point to plan-based, you steer the sub-project by plan. If at least three point to iterative, you steer it iteratively. At two against two, the undertaking is cut too large, and it is worth splitting it into parts before choosing the method.

## Where do hybrid projects fail?

Hybrid projects fail at the interfaces between the parts. Four interfaces decide: plan and backlog; budget and scope; report and reality; roles and accountability.

At the interface of plan and backlog the most frequent error arises: the plan contains functions with dates, the backlog contains work in cycles, and nobody holds the two together. A shared level of milestones phrased as outcomes, such as "pilot line in operation", closes the gap. The backlog then supplies the pieces that lead to the milestone. The article on [Big Room Planning](/en/blog/big-room-planning-dependencies/) shows how teams resolve dependencies in this setting.

At the interface of budget and scope, two logics collide. The plan assumes a fixed scope and a fixed budget, while iterative work adjusts the scope. The way out is a budget released in tranches, each after a review with a visible result, and a scope graded into must-have and nice-to-have. The frame then stands firm, and the team keeps room to adapt.

With report and reality a silent error appears: the project reports traffic lights by plan while the teams work in sprints by value, and the two reports describe different things. A joint report uses a few indicators that apply in both worlds, such as lead time, the share of milestones reached and open dependencies.

With roles, finally, the question of who is accountable for the overall result must be answered. The project manager is accountable for frame and milestones, the Product Owner for the value of the iterative parts, and someone has to hold the interface between the two. In many organisations a delivery manager takes on that task.

## How do you introduce a hybrid project?

You introduce a hybrid project in five steps. First, the undertaking is split into parts and each part is assessed with the criteria from the table. Then leadership fixes the steering for each part and writes it down in a project charter that also names the transitions. In the third step the joint frame emerges from milestones as outcomes, released budget tranches and a report with shared indicators. In the fourth step the parts start with their respective methods, with iterative teams tying their rhythm to the milestones. In the fifth step the steering group meets at a fixed rhythm, for example every four weeks, checks the handovers and adjusts the assignment when the cost of change or the clarity has shifted.

Anyone who has to choose between two team methods inside the iterative parts will find the criteria in the article on [Scrum or Kanban](/en/blog/scrum-vs-kanban-which-method-fits/).

**Checklist for the interfaces**
- Are milestones phrased as outcomes that a third party can verify?
- Is the budget released in tranches, each after a visible result?
- Is there a report whose indicators apply to plan-based and iterative parts?
- Is someone named as accountable for the overall result who holds the handovers?
- Is the assignment of methods reviewed every four weeks?

## Which failure modes are typical?

The most frequent failure mode is waterfall with an agile facade. The organisation calls phases sprints and specifications backlogs but changes neither approvals nor reports, so the teams work to plan and merely use different names. The mirror image is agile busyness: teams iterate without a frame, and nobody can say when which result is promised. A third failure mode is the method war, in which traditional project managers and agile roles wrestle over responsibilities because no level connects them. In all three cases nobody has settled who decides where, and about what.

## Hybrid projects with Niehues Consulting

[Niehues Consulting](/en/) is a consultancy for AI management and organisation design from a delivery perspective, based in Düsseldorf. Founder Marin Niehues builds organisations that deliver, in projects from VC-funded scale-ups to DAX 40 corporations and in more than 20 countries on six continents. In the service area of delivery management and organisation design he works as delivery manager, project manager or product owner at exactly the interfaces at which hybrid undertakings are decided.

The approach follows the Niehues Delivery Model with three phases. For hybrid projects, two of its test questions matter: Who decides, who delivers, who uses? Which roles and decision paths as well as interfaces does operations need? The entry point is a free 30-minute initial consultation, which you can arrange through the [contact form](/en/#kontakt). The scope and terms of an engagement are discussed in the free initial consultation.

**Conclusion**
Hybrid project methods combine plan-based steering for parts with high cost of change and iterative steering for parts with high uncertainty. The assignment follows four criteria, and success is decided at four interfaces: plan and backlog; budget and scope; report and reality; roles and accountability. One person accountable for the overall result holds the handovers together.

**Sources**
- Royce: Managing the Development of Large Software Systems, Proceedings IEEE WESCON, 1970
- Schwaber, Sutherland: The Scrum Guide, 2020
- Project Management Institute: A Guide to the Project Management Body of Knowledge (PMBOK Guide), 7th edition, 2021
- AXELOS: PRINCE2 Agile, 2015

## Frequently asked questions

### What are hybrid project management methods?

Hybrid project management methods combine plan-based and agile elements in one undertaking. A typical setup is a fixed frame with milestones and approvals in which teams deliver iteratively. The method is chosen for each part of the undertaking according to cost of change, clarity of requirements and external constraints.

### When does a hybrid approach make sense?

A hybrid approach makes sense when an undertaking contains parts with high cost of change and parts with high uncertainty. Examples are plant construction with control software, product launches with fixed trade-fair dates and programmes with a fixed-price contract and open scope. For a uniform undertaking with uniform constraints, one method is enough.

### Can you use Scrum in a waterfall project?

Yes, Scrum can be used within a plan-based frame if the frame leaves room for iterations. The team works in sprints of one month at most towards a goal derived from the milestone. The Scrum Guide 2020 requires a Product Goal and makes the Product Owner accountable for the order of work.

### What is the difference between hybrid and agile?

Agile means iterative steering with short feedback loops, whereas hybrid means combining iterative and plan-based steering in one undertaking. A hybrid project contains agile parts but adds fixed milestones, budget tranches or approvals. The distinction follows the question of whether the whole undertaking or only parts of it are steered iteratively.

### How do you plan a hybrid project?

A hybrid project is split into parts, and each part is assessed and given a form of steering. The joint frame consists of milestones as outcomes, budget tranches and a report with shared indicators. Teams plan within their own iterations.

### How do you report in a hybrid project?

A hybrid report uses a few indicators that apply in both worlds, such as lead time, the share of milestones reached and open dependencies. Traffic lights by plan next to sprint reports create contradictory pictures. A joint steering meeting every four weeks connects both views.

### Who is responsible for a hybrid project?

Responsibility for the overall result lies with a named person who connects frame and iterations, in many organisations a delivery manager. The project manager is accountable for milestones and approvals, the Product Owner for the value of the iterative parts. Without that connection, two reporting lines with different goals emerge.

### What is PRINCE2 Agile?

PRINCE2 Agile is an extension of the PRINCE2 method published in 2015 that adds agile techniques and links the method's frame with Scrum or Kanban in delivery. It shows that combinations of frame and iteration are described by the method owners themselves. In practice, the assignment of accountabilities between frame and team counts.